ML: What is the current status of the Orissa coal block allotted to GMR Energy in 2008? Will the delay in coal mining affect your power projects?
RK: For the Orissa coal block, we have already formed a joint venture company. Usually for any mine, pre-development activities take around two-three years’ time and we need a number of clearances like forest, exploration and environmental clearances. The process is going on. As far as our power project is concerned, the work is going on as per schedule. Since we have sufficient coal linkages in place, our power projects will not be affected due to delay in coal mining at the Orissa block.
ML: State-run CIL has been trying to ensure continuous coal supply across the country. Do you think CIL’s efforts are enough?
RK: CIL is looking to import substantial quantity of coal from abroad, so I think these steps would take care of coal supply in the medium to short term. However, I personally feel that CIL should seriously think of improving its productivity and also undertake more underground mining.
ML: A number of power companies have raised money from the capital market for expansions. But do you think that these companies have overlooked problems like the coal supply shortage?
RK: We have been hearing that there is a coal shortage. However, with all the action that CIL is undertaking, inclusive of the support from imported coal, coal shortage is a temporary problem and I am sure coal shortage will not come in the way of power projects.